Choosing a VFD for Air Handling Units in HVAC Systems
How to choose the best VFD for an air handling unit: a checklist for fan duty, current, BACnet or Modbus, PID, EMC, IP rating, fire mode…
Read moreA VSD startup procedure in eight phases, from pre-power checks and auto-tuning to load tests and handover, with a VFD commissioning checklist table.
A VSD startup procedure runs in eight phases. Check the installation with the power off, power up with all control inputs open, then enter the motor nameplate data and auto-tune. Set ramps, limits and protections, test every input and output, and run the motor with no load before the real load. Finish by saving the parameters and handing over the records.

Variable speed drive commissioning turns an installed drive into a working, tested system. The drive must know the motor, the motor must turn the right way, and every protection must suit the load.
The manufacturers set the bar high. Schneider Electric’s ATV630 installation manual asks for tests of all operating states, operating conditions and potential error situations. It also warns against running the product with unknown settings or data.
This guide gives the general steps shared by the Himel, Schneider Electric and WEG manuals. Parameter names and menus differ by model, so always follow your drive’s manual.
Safety note: Commissioning is live electrical work. It must be done by a qualified, licensed electrical worker following the manufacturer’s manual. The Energy Market Authority states that only licensed electrical workers may install, operate, inspect and test electrical installations under their licence.
The phases always run in the same order. Each one depends on the one before it, so do not skip ahead.

Do these checks with the power isolated. Schneider Electric’s manual says to lock all power switches open. Then wait 15 minutes for the DC bus capacitors to discharge, and verify the absence of voltage.
WEG’s ADV200 guide lists the final checks before energising. The supply voltage must be correct, and all control inputs must be open. Only then apply power.
Before you switch on, clear the area around the driven machine. Schneider Electric also asks for a working emergency stop within reach of everyone involved.
Watch the display as the drive boots. If the drive came from another job, its settings may be unknown. Schneider Electric warns against running a drive with unknown settings. Its programming manual shows how to restore the factory settings at any time. As general practice, take the same care with any drive of unknown history, such as a Himel X Series VSD Singapore unit from a previous trial.
The drive needs the motor’s rated data to control it well. Read the values from the motor nameplate, not from drawings.
On the ATV630, the Motor Standard parameter comes first. It presets the drive for 50 Hz IEC or 60 Hz NEMA motors. Schneider Electric warns that changing it later means repeating the configuration.
Table 1 shows how three manuals name this step, including the Schneider Altivar Process ATV630 Singapore range.
| Drive | Where you enter motor data | Data asked for | Name of the tuning step |
|---|---|---|---|
| Himel Basic Series VSD | Motor parameter group | Rated power, current, speed, frequency, voltage and motor poles | Parameter self-learning |
| Schneider Electric ATV630 | Simply Start menu | Motor standard, nominal power, voltage, current, frequency and speed | Autotuning, a standstill motor tune |
| WEG ADV200 | Startup Wizard | Rated voltage, frequency, current, speed, power and power factor | Autotune rotation or Autotune still |
Also set the motor thermal current. Schneider Electric says to set it to the rated current on the nameplate.
Auto-tuning measures the motor’s electrical characteristics. The drive then uses these values to control the motor accurately.
Tip: If you change any motor parameter after tuning, tune again. Schneider Electric states this in its programming manual.
Ramps control how fast the motor speeds up and slows down. On the ATV630, acceleration time is measured from 0 Hz to the motor’s rated frequency. The factory setting is 10 seconds.
Schneider Electric says to set ramps to suit the application, and to consider load inertia. As a general rule, a heavy fan needs a longer ramp than a small pump.
Next, set the speed limits. Himel’s manual requires the maximum output frequency to be at least the upper limit, which must be at least the lower limit. On the ATV630, Schneider Electric recommends a maximum frequency of at least 110% of high speed.
Then set motor protection. WEG states the motor must be protected against overloads. On the ATV630, choose a thermal mode for a self-ventilated or a fan-cooled motor.
Now prove that every signal reaches the drive. First, choose 2-wire or 3-wire control to match your start and stop wiring. The checks below are general practice.
The ATV630’s I/O Map menu shows each input’s assigned function and present state. WEG advises a meter with an internal resistance of at least 10 kΩ/V for signal voltages.
As general practice, start with the motor uncoupled where you can. Schneider Electric warns to anticipate movement in an unintended direction.
WEG’s guide describes a first functional test. Set the analogue reference to minimum, close the Enable contact, then close the forward command. Raise the reference gradually and check the direction of rotation.
If the direction is wrong, WEG says to stop the drive, disconnect the power and swap two motor phases. The ATV630 can instead use its output phase rotation parameter, which inverts two motor phases.
WEG then asks you to check output voltage, current and frequency against the motor and the reference. As general practice, couple the load and repeat across the speed range. Record motor current, speed and any warnings, and test every stop method.
The job is not finished until the settings are saved and recorded. WEG’s keypad has five memory areas for saving parameters. The ATV630 has a Save Configuration function for later restoring.
As general practice for any industrial variable speed drive in Singapore, hand over a record pack. It should include the final parameter list, tuning results and test readings. A saved record helps if the drive is ever replaced. Our guide to replacing a variable speed drive shows why.
Follow the same eight phases. Then add these general pump checks before the load test.
Sizing comes before all of this. See our guide to sizing a VFD for a pump. For fans, read our article on VFDs on cooling towers.
Use Table 2 as a sign-off sheet. Each row needs a name and a date.
| Phase | Check | Record |
|---|---|---|
| 1. Pre-power | Clearances, fixing torque, cover fitted | Done or not done |
| 1. Pre-power | Supply and motor cables on correct terminals | Done or not done |
| 1. Pre-power | All protective earth conductors connected | Earth reading |
| 1. Pre-power | Power and control wiring separated | Done or not done |
| 1. Pre-power | Fuses and breakers correctly rated | Ratings fitted |
| 2. Power-up | Supply voltage correct, control inputs open | Voltage measured |
| 2. Power-up | Factory settings restored if history unknown | Done or not done |
| 3. Nameplate | Motor rated data entered | Values entered |
| 3. Nameplate | Motor thermal current set | Value entered |
| 4. Auto-tune | Tune completed and saved | Tune type used |
| 5. Settings | Ramps, speed limits, thermal protection set | Values set |
| 6. I/O | Every input and output proven | Points tested |
| 7. Run test | Direction correct with no load | Done or not done |
| 7. Run test | Current and speed under load | Readings |
| 7. Run test | All stop methods work | Done or not done |
| 8. Handover | Parameters saved and record pack issued | File name |
This checklist sits alongside the panel checks for motor starter panel components.
Trans-Digi’s home page states that it provides supply, installation, testing and commissioning for projects. Our testing and commissioning service configures drive and soft starter parameters for the actual motor, load and application. It also covers functional testing, BMS interface checks and handover records.
We work with panel builders, M&E contractors and consultants. If you need a VFD for panel builders in Singapore, we can help from selection through to live commissioning. See Trans-Digi’s services page for the full scope.
A careful startup protects the motor, the load and the people around it. If you would like support on your next project, we are ready to help.
Commissioning involves checking the installation with the power off, then a controlled first power-up. You enter the motor nameplate data, run auto-tuning and set ramps, limits and protections. Next you test every input and output. Finally you run the motor with no load, then under load, and save and record the parameters.
The work must be done by a qualified, licensed electrical worker following the manufacturer’s manual. The Energy Market Authority states that only licensed electrical workers may install, operate, inspect and test electrical installations under their licence. The class of licence needed depends on the size of the installation.
It depends on the tune type. WEG’s rotating tune is for an uncoupled motor, or one carrying no more than 5% load, and gives the most accurate data. Its standstill tune suits a coupled motor. Schneider Electric asks for the motor to be cold and connected. Follow your drive’s manual.
Check your drive’s manual before any insulation test. WEG states that no dielectric tests should be carried out on parts of the drive. Follow the manufacturer’s method for isolating the drive, and have a licensed electrical worker carry out the test.
Keep the final parameter list, the tuning results and the test readings, such as motor current under load. Save the parameters in the drive and on the keypad or software where the drive allows it. A signed checklist, like Table 2 above, shows each check was completed and by whom.
Follow the standard eight phases, then add pump checks. Confirm rotation before the pump runs on water, and set a minimum speed that still delivers flow. Set up pump protection such as dry run and low flow monitoring where the drive provides it. Then test across the full duty range.